progressive-estimation

Estimate AI-assisted and hybrid human+agent development work with explicit PERT assumptions and calibration feedback loops

Published by sickn33 ↗sickn33/agentic-awesome-skills

Try your first task

A source-grounded starter task has not been verified for this skill yet.

SKILL.md

name: progressive-estimationdescription: "Estimate AI-assisted and hybrid human+agent development work with explicit PERT assumptions and calibration feedback loops"category: project-managementrisk: safesource: communitydate_added: "2026-03-10"author: Enreigntags:   - estimation  - project-management  - pert  - sprint-planning  - ai-agentstools:   - claude

Progressive Estimation

Estimate AI-assisted and hybrid human+agent development work using three-point estimates, stated uncertainty assumptions and calibration feedback loops.

Overview

Progressive Estimation adapts to your team's working mode — human-only, hybrid, or agent-first — choosing explicit assumptions for each. Estimates remain uncertain and require local calibration.

When to Use This Skill

  • Estimating development tasks where AI agents handle part of the work
  • Sprint planning with hybrid human+agent teams
  • Batch sizing a backlog (handles 5 or 500 issues)
  • Staffing and capacity planning with agent multipliers
  • Release date forecasting with confidence intervals

How It Works

  1. Mode Detection — Determines if the team works human-only, hybrid, or agent-first
  2. Task Classification — Categorizes by size (XS–XL), complexity, and risk
  3. Formula Application — Applies locally measured multipliers when available, or clearly labeled scenarios
  4. PERT Calculation — Produces expected values using three-point estimation
  5. Confidence Bands — Generates percentiles only with a specified, calibrated forecast model
  6. Output Formatting — Formats for Linear, JIRA, ClickUp, GitHub Issues, Monday, or GitLab
  7. Calibration — Feeds back actuals to improve future estimates

Examples

Single task:

"Estimate building a REST API with authentication using Claude Code"

Batch mode:

"Estimate these 12 JIRA tickets for our next sprint"

With context:

"We have 3 developers using AI agents for ~60% of implementation. Estimate this feature."

Estimation procedure

Record scope, dependencies, acceptance criteria and whether durations mean effort or elapsed time. Elicit optimistic O, most likely M and pessimistic P in the same units, with O ≤ M ≤ P. A conventional PERT approximation is E = (O + 4M + P)/6 and SD ≈ (P − O)/6; these are modeling assumptions, not observed certainty. For O=2, M=4, P=12 hours, E=5 hours and SD≈1.67 hours. Record the assumptions behind each bound.

Do not derive P50/P75/P90 directly from the mean or label a range a confidence interval without a stated distribution and method. For a project forecast include dependencies, correlated risks, review/queue time and limited human capacity. Use actual comparable completed tasks to calibrate AI multipliers; absent data, present explicit scenarios rather than claiming a research-backed speedup. Report actuals against the original scope and revise future forecasts. This guide does not bundle an estimation engine or calibration database.

Best Practices

  • Start with a single task to calibrate before moving to batch mode
  • Feed back actual completion times to improve the calibration system
  • Use "instant mode" for quick T-shirt sizing without full PERT analysis
  • Be explicit about team composition and agent usage percentage

Common Pitfalls

  • Problem: Overconfident estimates Solution: Use P75 or P90 for commitments, not P50

  • Problem: Missing context Solution: The skill asks clarifying questions — provide team size and agent usage

  • Problem: Stale calibration Solution: Re-calibrate when team composition or tooling changes significantly

Related Skills

  • @sprint-planning - Sprint planning and backlog management
  • @project-management - General project management workflows
  • @capacity-planning - Team velocity and capacity planning

Additional Resources

Limitations

  • Use this skill only when the task clearly matches the scope described above.
  • Do not treat the output as a substitute for environment-specific validation, testing, or expert review.
  • Stop and ask for clarification if required inputs, permissions, safety boundaries, or success criteria are missing.