Run an NPI phase-gate review for EVT, DVT, or PVT — exit criteria per phase, open-issue triage, yield readout, waiver discipline, and a go/no-go call. Use when asked to run a gate review, decide EVT exit or DVT entry, review build results, assess whether to proceed to the next build, or triage open issues before a phase gate. Produces a gate review document with criteria scoring, waiver register, yield analysis, and a defensible go/conditional-go/no-go recommendation.
Start a fresh conversation. Replace the highlighted placeholders.
Use evt-dvt-pvt-gate-review to review the [EVT/DVT/PVT gate] for [product] using build results and open issues, and deliver a scored gate-review document with yield analysis, issue/waiver register, risks, and a go/conditional-go/no-go recommendation; mark missing evidence as unverified rather than passing it.
Required inputs
[EVT/DVT/PVT gate]
[product]
User-approved starter prompt based on a pinned source version; check current skill requirements before running. Task evidence ↗
SKILL.md
name: evt-dvt-pvt-gate-reviewdescription: "Run an NPI phase-gate review for EVT, DVT, or PVT — exit criteria per phase, open-issue triage, yield readout, waiver discipline, and a go/no-go call. Use when asked to run a gate review, decide EVT exit or DVT entry, review build results, assess whether to proceed to the next build, or triage open issues before a phase gate. Produces a gate review document with criteria scoring, waiver register, yield analysis, and a defensible go/conditional-go/no-go recommendation."
EVT/DVT/PVT Gate Review Skill
Phase gates exist because hardware mistakes compound: an issue waved through EVT costs 10× at DVT and 100× in the field. This skill runs the gate the way a strong NPI lead does — score against written exit criteria, triage every open issue as blocker or waiver, read yield with its denominator, and make a recommendation someone can be held to.
What This Skill Produces
A scored exit-criteria checklist for the phase under review
An open-issue triage table (blocker / waiver / defer) with rationale
A yield readout by test station with failure Pareto
A waiver register with class, owner, expiry, and containment
A go / conditional-go / no-go recommendation with the conditions written down
Required Inputs
Ask for these if not provided; run the review on partial data but mark unverifiable criteria [no data — cannot score], never assumed-pass:
Which gate — EVT, DVT, or PVT exit (or entry to the next phase)
Build results — units built, units passing, failures by test station or symptom
Open issue list — bugs/defects with severity and status
Exit criteria if the program has them; otherwise use the reference set below and say so
Schedule pressure — the real next-build date, so the recommendation is honest about trade-offs
Gate Framework
Reference exit criteria (adapt to the program's own if provided):
Criterion
EVT exit
DVT exit
PVT exit
Proves
Design works (works-like)
Design is reliable & certifiable (looks-like/works-like)
Factory can build it at rate
Tooling
Proto/soft tooling OK
Off near-final tooling
Production tooling, production line
Functional yield
≥ ~80% with failures understood
≥ ~90%
≥ ~95%, stable across line runs
Reliability
Key risks tested (thermal, drop samples)
Full reliability suite passed (drop, tumble, thermal cycle, HALT as applicable)
ORT started; Cpk ≥ 1.33 on critical dimensions
Certs
Pre-scan risks identified
EMC/safety pre-scans passed
Cert filings submitted/granted
Cost
BOM within ~10% of target
BOM within ~5%, cost-downs planned
COGS at target with yield burdened in
Open issues
No unresolved blockers
No blockers; waivers classed & expiring
Only Class C waivers, all with limit samples
Issue triage. Every open issue gets exactly one bucket: Blocker (fails a criterion, fix before gate), Waiver requested (pass the gate with the defect, under discipline below), Defer (not a gate criterion — but say why).
Waiver discipline. Class A — safety/regulatory/data-loss: never waivable. Class B — functional/reliability: waivable only with named owner, expiry date (a specific build or date at which it's fixed or the program stops), and containment for affected units. Class C — cosmetic: waivable against an approved limit sample.
Output Format
Gate review: [product] — [EVT/DVT/PVT] exit
Recommendation — Go / Conditional go (conditions listed, each with owner + date) / No-go (earliest re-review)